Flood Recovery Campus Status Report

The Flood of 2016 damaged six schools and multiple school district facilities. The following information will be updated periodically in order to keep the public informed about our recovery. 

 

FLOOD RECOVERY CAMPUS STATUS REPORT

Updated 08-01-20

Click here for Frequently Asked Questions | Click here for the a one-page flood recovery update

GALVEZ PRIMARY | GALVEZ MIDDLE | LAKE ELEMENTARY | ST. AMANT PRIMARY | ST. AMANT MIDDLE | ST. AMANT HIGH

 

GALVEZ PRIMARY

 

Temporary Buildings on Home Campus

  • Galvez Primary Site Plan
  • Structures: Administration Building, Library, Dining Hall, Classrooms (3 Pods of 10 Classrooms)
  • Work Complete: Modular Buildings Delivered and Installed, Installation of Classroom Technology, Construction of Covered Walkways, Restoration of Flooded Kitchen, Connection of Utilities, Delivery of Furniture, Relocation of Teacher Materials, Inspection and Permitting by All Public Agencies
  • Move-In Date: March 2, 2017 

Permanent Repairs

  • Structures: Administration Building, Library, Dining Hall, All Permanent Classroom Buildings
  • Work Complete: Flood Restoration of all buildings
  • Move-In Date: July 9, 2018

DEMOBILIZATION OF TEMPORARY BUILDINGS

  • Structures: Administration Building, Library, Dining Hall, Classrooms (4 Pods of 8 Classrooms and 2 Pods of 10 Classrooms) and Band Hall
  • Work Complete: Removal of Modular Buildings, Classroom Technology, Covered Walkways and Associated Utilities
  • Completion Date: January 7, 2019 

DEMOBILIZATION OF TEMPORARY BUILDINGS

  • Structures: Modular building with two (2) Classrooms.
  • Work Complete: Remove and Replace flood-damaged modular building
  • Move-In Date: July 23, 2019

GALVEZ MIDDLE

Temporary Buildings on Home Campus

  • Galvez Middle Site Plan
  • Structures: Library, Dining Hall, Classrooms (3 Pods of 8 Classrooms plus 1 T-Building of 2 Classrooms) and Band Hall
  • Work Complete: Administration Offices (Building not Impacted by Flood); Modular Buildings Delivered and Installed, Installation of Classroom Technology, Construction of Covered Walkways, Restoration of Flooded Kitchen, Delivery of Furniture, Connection of Utilities, Inspection and Permitting 
  • Move-In Date: Mar. 13, 2017

Permanent Repairs

  • Work Complete: Flood Assessments, Architect Selection
  • Work Complete: Flood Restoration of all buildings, Interior Renovation of the Old Gym with Mechanical Upgrades and Interior Upgrades to Second Floor of Classroom Building C
  • Target Completion: August 2018

 DEMOBILIZATION OF TEMPORARY BUILDINGS

  • Structures: Library, Dining Hall, Classrooms (3 Pods of 8 Classrooms plus 1 T-Building of 2 Classrooms) and Band Hall
  • Work Complete: Removal of Modular Buildings, Classroom Technology, Covered Walkways, and Associated Utilities 
  • Completion Date: November 11, 2019

 

LAKE ELEMENTARY

Temporary Buildings on Home Campus

  • Lake Elementary Site Plan
  • Structures: Administration Building, Library, Dining Hall, Classrooms (4 Pods of 8 Classrooms and 2 Pods of 10 Classrooms) and Band Hall
  • Work Complete: Modular Buildings Delivered and Installed, Installation of Classroom Technology, Construction of Covered Walkways, Restoration of Flooded Kitchen, Connection of Utilities, Delivery of Furniture, Inspection and Permitting, Relocation of Teacher Materials
  • Move-In Date: Mar. 6, 2017 

Permanent Repairs

  • Structures: Main Classroom Building
  • Work Complete: Flood Restoration of all buildings
  • Move-In Date: July 5, 2018

DEMOBILIZATION OF TEMPORARY BUILDINGS

  • Structures: Administration Building, Library, Dining Hall, Classrooms (4 Pods of 8 Classrooms and 2 Pods of 10 Classrooms) and Band Hall
  • Work Complete: Removal of Modular Buildings, Classroom Technology, Covered Walkways and Associated Utilities
  • Completion Date: April 4, 2019  

MODULAR CLASSROOM ADDITION

  • Structures: Modular building with four (4) Classrooms.
  • Work Complete: Remove and Replace flood-damaged modular buildings
  • Move-In Date: January 24, 2020

 

ST. AMANT PRIMARY

Permanent Repairs

  • Structures: Classroom Buildings, Administrative Suite and Cafetorium
  • Work Complete: Flood Restoration of all buildings and new Mechanical Building with new Mechanical Equipment
  • Completion Date: July 31, 2017

  

ST. AMANT MIDDLE

Temporary Buildings on Home Campus

  • Structure: Band Hall
  • Work Complete: Buildings Occupied and Not Impacted by Flood (Administration, Library, Main Classroom Buildings, Main Gym), Temporary Restoration of Kitchen, Delivery and Installation of Temporary Band Hall, Inspection and Permitting
  • Work Pending: Complete
  • Completion Date: Mar. 6, 2017 

Permanent Repairs

  • Structures: Classroom Buildings, Band Building, Weight Room, Concession Buildings, New Gym and Administrative Suite
  • Work Complete: Flood Restoration of all buildings
  • Completion Date: August 31, 2017

 

ST. AMANT HIGH

Temporary Buildings on Home Campus

  • St. Amant High Site Plan
  • Structures: Classrooms (6 Pods of 10 Classrooms and 5 T-buildings of 2 Classrooms) 2 Band Halls
  • Work Complete: Freshman Academy (Includes Administration Offices, Classrooms, Cafeteria and Kitchen); Office Furniture Delivered; Modular Buildings Delivered and Installed, Construction of Covered Walkways, Installation of Classroom Technology, Connection of Utilities, Inspections and Permitting, Relocation of Teacher Materials, Installation and Permitting of Band Hall
  • Move-In Date: Feb. 13, 2017 

Permanent Repairs

  • Structures: Main Building, Classroom Buildings, New Gym, Gold Dome, ROTC/AG, Field House, Weight Room and Softball Locker Room.
  • Work Complete: Flood Restoration of all buildings and new ROTC Modular Building
  • Completion Date: Phase 1: March 13, 2018; Phase 2: July 13, 2018; Phase 3: December 21, 2018

DEMOBILIZATION OF TEMPORARY BUILDINGS

  • Structures: Administration Building, Library, Dining Hall, Classrooms (3 Pods of 10 Classrooms)
  • Work Complete: Removal of Modular Buildings, Classroom Technology, Covered Walkways, and Associated Utilities
  • Completion Date: September 12, 2019