The Flood of 2016 damaged six schools and multiple school district facilities. The following information will be updated periodically in order to keep the public informed about our recovery. 

 

FLOOD RECOVERY CAMPUS STATUS REPORT

Updated 7-7-17 (changes in blue)

Click here for Frequently Asked Questions | Click here for the a one-page flood recovery upate

GALVEZ PRIMARY | GALVEZ MIDDLE | LAKE ELEMENTARY | ST. AMANT PRIMARY | ST. AMANT MIDDLE | ST. AMANT HIGH


GALVEZ PRIMARY


Temporary Buildings on Home Campus

  • Site Plan
  • Structures: Administration Building, Library, Dining Hall, Classrooms (3 Pods of 10 Classrooms)
  • Work Complete: Modular Buildings Delivered and Installed, Installation of Classroom Technology, Construction of Covered Walkways, Restoration of Flooded Kitchen, Connection of Utilities, Delivery of Furniture, Relocation of Teacher Materials, Inspection and Permitting by All Public Agencies
  • Move-In Date: Mar. 2, 2017 

Permanent Repairs

  • Work Complete: Flood Assessments, Architect Selection
  • Work in Progress: Design
  • Target Completion Date: To Be Determined 

 

GALVEZ MIDDLE

Temporary Buildings on Home Campus

  • Site Plan
  • Structures: Library, Dining Hall, Classrooms (3 Pods of 8 Classrooms plus 1 T-Building of 2 Classrooms) and Band Hall
  • Work Complete: Administration Offices (Building not Impacted by Flood); Modular Buildings Delivered and Installed, Installation of Classroom Technology, Construction of Covered Walkways, Restoration of Flooded Kitchen , Delivery of Furniture, Connection of Utilities, Inspection and Permitting 
  • Move-In Date: Mar. 13, 2017
Permanent Repairs
  • Work Complete: Flood Assessments, Architect Selection
  • Work in Progress: Design
  • Target Completion Date: To Be Determined 

 

LAKE ELEMENTARY

Temporary Buildings on Home Campus

  • Site Plan
  • Structures: Administration Building, Library, Dining Hall, Classrooms (4 Pods of 8 Classrooms and 2 Pods of 10 Classrooms) and Band Hall
  • Work Complete: Modular Buildings Delivered and Installed, Installation of Classroom Technology, Construction of Covered Walkways, Restoration of Flooded Kitchen, Connection of Utilities, Delivery of Furniture, Inspection and Permitting, Relocation of Teacher Materials
  • Move-In Date: Mar. 6, 2017 

Permanent Repairs

  • Work Complete: Flood Assessments, Architect Selection, Design
  • Work in Progress: Preparing for construction bid
  • Target Completion Date: To Be Determined 

  

ST. AMANT PRIMARY

Current School Locations

  • PreK – 5th Grade Students at the Old RPCC Campus

Permanent Repairs

  • Work Complete: Flood Assessments, Architect Selection, Design, Construction Bid
  • Work in Progress: Construction Underway
  • Target Completion Date: July 31, 2017 (subject to weather delays)

  

ST. AMANT MIDDLE

Current School Location

  • Home Campus

Temporary Buildings on Home Campus

  • Structure: Band Hall
  • Work Complete: Buildings Occupied and Not Impacted by Flood (Administration, Library, Main Classroom Buildings, Main Gym), Temporary Restoration of Kitchen, Delivery and Installation of Temporary Band Hall, Inspection and Permitting
  • Work in Progress: 
  • Work Pending: 
  • Completion Date: Mar. 6, 2017 

Permanent Repairs

  • Work Complete: Flood Assessments, Architect Selection, Design, Construction Bid
  • Work in Progress: Construction Underway
  • Target Completion Date: Aug. 21, 2017 (Kitchen/Cafeteria to be complete by July 31, 2017)

 

ST. AMANT HIGH


Temporary Buildings on Home Campus

  • Site Plan
  • Structures: Classrooms (6 Pods of 10 Classrooms and 5 T-buildings of 2 Classrooms) 2 Band Halls
  • Work Complete: Freshman Academy (Includes Administration Offices, Classrooms, Cafeteria and Kitchen); Office Furniture Delivered; Modular Buildings Delivered and Installed, Construction of Covered Walkways, Installation of Classroom Technology, Connection of Utilities, Inspections and Permitting, Relocation of Teacher Materials, Installation and Permitting of Band Hall
  • Move-In Date: Feb. 13, 2017 

Permanent Repairs

  • Work Complete: Flood Assessments, Architect Selection
  • Work in Progress: Design
  • Target Completion Date: To Be Determined